120 sq ft of structural and waterproofing repairs to the elevated walkway bridge serving Building 35, including wood framing replacement, new concrete, and a multi-layer waterproofing system to restore structural integrity and prevent future water intrusion.

Project Duration: 3 Weeks

Key challenges overcome:

  • Uninterrupted Access: Installed a temporary ADA-accessible pedestrian bridge with guardrails, maintaining safe access for all occupied units, including wheelchair users, throughout construction.
  • Structural Restoration: Replaced deteriorated wood framing and installed new structural members and concrete in accordance with approved engineering details and SB 721 requirements.
  • Environmental Compliance: Coordinated with licensed environmental contractors to safely manage lead and asbestos under full EPA RRP compliance.
  • Construction Logistics: Sequenced work to keep the only building entrance in service throughout construction, completing the project in three weeks with zero safety incidents.