280 sq ft of structural repairs in the garage, including new concrete footings and post girder reconstruction, resolved settlement caused by unstable soil conditions and restored the building’s structural support system.

Project Duration: 5 Weeks

Key challenges overcome:

  • Concealed Structural Conditions: Discovered voids beneath several existing footings during excavation, requiring engineered fill, soil compaction, supplemental shoring, and redesigned footings in coordination with the Engineer of Record.
  • Temporary Shoring: Installed approximately ten temporary shoring locations after selective slab demolition and soil stabilization, keeping the structure safely supported throughout construction.
  • Resident Coordination: Relocated, protected, and restored resident storage areas within the garage, maintaining continuous communication to minimize disruption.